The FHA 203-k mortgage program can be used for one-to-four unit dwellings.

Yes, however, condominium rehabilitation is subject to the following conditions:

a) Owner/occupant and qualified non-profit borrowers only;

b) Rehabilitation is limited only to the interior of the unit. Mortgage proceeds are not to be used for the rehabilitation of exteriors or other areas which are the responsibility of the condominium association, except for the installation of firewalls in the attic for the unit;

c) Only the lesser of five units per condominium association, or 25 percent of the total number of units, can be undergoing rehabilitation at any one time;

d) The maximum mortgage amount cannot exceed 100 percent of after-improved value. After rehabilitation is complete, the individual buildings within the condominium must not contain more than four units. By law, FHA 203(k) loans can only be used to rehabilitate units in one-to-four unit structures. However, this does not mean that the condominium project, as a whole, can only have four units or that all individual structures must be detached.

Example: A project might consist of six buildings each containing four units, for a total of 24 units in the project and, thus, be eligible for an FHA 203(k) loan. Likewise, a project could contain a row of more than four attached townhouses and be eligible for a FHA 203(k) loan because HUD considers each townhouse as one structure, provided each unit is separated by a 1 1/2 hour firewall (from foundation up to the roof). Similar to a project with a condominium unit with a mortgage insured under Section 234(c) of the National Housing Act, the condominium project must be approved by HUD prior to the closing of any individual mortgages on the condominium units.

Yes. However, release of loan proceeds for the existing structure on the non-mortgaged property is not allowed until the new foundation has been properly inspected and the dwelling has been properly placed and secured to the new foundation. At closing, funds would be released to purchase the site and the rest of the mortgage proceeds would be placed in the Rehabilitation Escrow Account. The borrower would have the site prepared to accept the dwelling. The first release would be based on the improvements made to the site, including the installation of the existing structure on the new foundation.

  • Structural alterations and reconstruction (e.g., repair or replacement of structural damage, chimney repair, additions to the structure, installation of an additional bath(s), skylights, finished attics and/or basements, repair of termite damage and the treatment against termites or other insect infestation, etc.).

  • Changes for improved functions and modernization (e.g., remodeled bathrooms and kitchens, including permanently installed appliances, i.e., built-in range and/or oven, range hood, microwave, dishwasher).

  • Elimination of health and safety hazards (including the resolution of defective paint surfaces or lead-based paint problems on homes built prior to 1978).

  • Changes for aesthetic appeal and elimination of obsolescence (e.g., new exterior siding, adding a second story to the home, covered porch, stair railings, attached carport).

  • Reconditioning or replacement of plumbing (including connecting to public water and/or sewer system), heating, air conditioning and electrical systems. Installation of new plumbing fixtures is acceptable, including interior whirlpool bathtubs.

  • Installation of well and/or septic system. The well or septic system must be installed or repaired prior to beginning any other repairs to the property. A property less than 1/2 acre with a separate well or septic system is not acceptable; also, a property less than 1 acre with both a well and a septic system is unacceptable. Lots smaller than these sizes, usually have problems in the future; however, the local HUD Field Office can approve smaller lot size requirements where the local health authority can justify smaller lots. The installation of a new well, or the repair of an existing well (used for the primary water source to the property) is allowed, provided there is adequate documentation to show it is likely the well will produce enough potable water for the occupants. (A well log of surrounding properties from the local health authority is acceptable documentation.)

  • Roofing, gutters and downspouts.

  • Flooring, tiling and carpeting.

  • Energy conservation improvements (e.g., new double pane windows, steel insulated exterior doors, insulation, solar domestic hot water systems, caulking and weather stripping, etc.).

  • Major landscape work and site improvement (e.g., patios, decks and terraces that improve the value of the property equal to the dollar amount spent on the improvements or required to preserve the property from erosion). The correction of grading and drainage problems is also acceptable. Tree removal is acceptable if the tree is a safety hazard to the property. Repair of existing walks and driveway is acceptable if it may affect the safety of the property. (Fencing, new walks and driveways, and general landscape work (i.e., trees, shrubs, seeding or sodding) cannot be in the first $5000 requirement.)

  • Improvements for accessibility to a disabled person (e.g., remodeling kitchens and baths for wheelchair access, lowering kitchen cabinets, installing wider doors and exterior ramps, etc.). Related fixtures such as new cooking ranges, refrigerators, and other appurtenances, as well as general painting are also eligible; however, it must be in addition to the $5,000 requirement.

Yes, however, a new unit must be attached to the existing dwelling, and must comply with HUD's Minimum Property Standards in 24 CFR 200.926d and all local codes and ordinances.

Yes, the Rehabilitation Loan Agreement contains three provisions concerning the timeliness of the work. The work must begin within 30 days of execution of the Agreement. The work must not cease prior to completion for more than 30 consecutive days. The work is to be completed within the allotted time shown in the Agreement (not to exceed six months); the lender should not allow a time period longer than that required to complete the work.

The lender may refuse to make further releases from the Rehabilitation Escrow Account. The funds remaining in the Account can be applied to reduce the mortgage principal. Also, the lender has the option to call the mortgage loan due and payable.

Yes. The improvements must comply with HUD's Minimum Property Standards and all local codes and ordinances.

Typically, yes. On properties older than 30 years and over $7,500 in rehabilitation costs, the cost estimate must include a contingency reserve. The reserve must be a minimum of ten (10) percent of the cost of rehabilitation; however, the contingency reserve may not exceed twenty (20) percent where major remodeling is contemplated. If utilities were not turned on for inspection, a minimum fifteen (15) percent is required.

As many as five releases (four plus a final) can be scheduled. The number of releases is normally dictated by the cash-flow requirements of the contractor. An inspection is always required with a scheduled release; however, inspections may be scheduled more often than releases if necessary to ensure compliance with the architectural exhibits, HUD's Minimum Property Standards and all local codes and ordinances. If the cost of rehabilitation exceeds $ 10,000, then additional draw inspections may be authorized under certain circumstances.

Yes. The changes must be approved by HUD or a DE lender prior to beginning the work. If the change affects the health, safety or necessity of the dwelling, the contingency reserve can be used to pay for the change. However, if the health, safety or necessity of the dwelling is not affected and an increase in cost occurs, the borrower must apply monies into the contingency reserve fund to pay for the change. Should the change result in a reduced cost of rehabilitation, the difference will be placed in the contingency reserve fund; if unused, it will be applied as a mortgage prepayment after completion of construction.

No. This emphasizes the importance of carefully selecting a contractor who will accurately estimate the cost of the improvements and satisfactorily complete the rehabilitation at or below the estimate.

If the cost estimates are completed within two weeks of signing the sales contract, the loan should close within 60 to 90 days, assuming there are no title problems and, of course, your borrower is qualified.

Yes. An Adjustable Rate Mortgage is available to an owner-occupant only. Investors and non-profits are not eligible for an ARM.

No. In October, 1996, the Department placed a moratorium on investor participation in the FHA 203(k) mortgage loan Rehabilitation Mortgage Program.

Yes. The same qualification requirements will be used as for an owner-occupant of the property

Yes. Up to six months of payments may be included in the mortgage if the property is not occupied during the rehabilitation period.

No. However, the building could be renovated and reduced to a four unit building.

Yes. A dwelling can be remodeled to improve the kitchen and bath to accommodate a wheelchair access. Wider doors and handicap ramps can also be included in the cost of rehabilitation.

No. However, if the borrower wants to do any work or be the general contractor, they must be qualified to do the work, and do it in a timely and workmanlike manner. It is very important that the work be done in a time frame that will assure the completion of the work that will be agreed upon in the Rehabilitation Loan Agreement (signed at closing). A borrower doing their own work can only be paid for the cost of the materials. Monies saved can be allocated to cost overruns or additional improvements.

The cost estimate must be the same as if a contractor is doing the work, in case the borrower cannot (for some reason) complete the work.

No. However, the savings can be transferred to cost overruns in other work items or can be used to make additional improvements to the property If the cost savings are not used, the money must be applied to the mortgage principal, but the mortgage payments will remain the same, because the loan has

already closed. To use the cost savings, it will be necessary for a Change Order to be completed and approved by the lender.

No. However, an exception can be allowed for kitchen and bath cabinetry, or floor covering, where a contract is established with the supplier and an order is placed with the manufacturer for delivery at a later date.

HUD allows fee inspectors to be an independent consultant with

the borrower. This is a time saver, because it can be completed in about two weeks. After this step is completed, closing should occur within 60 to 90 days.

Yes. However, it will take them between three to six months to complete. This slows down the process and will save only about $200, but waste a lot of valuable time. Hiring an independent consultant will help the closing occur within 60 to 90 days from completion of the Work Write-up.

Yes. A borrower can have not more than seven (7) units within a two-block radius of the property they want to purchase. However, if the property is in a local community area that has been designated for redevelopment or revitalization, then this seven-unit limitation does not apply.

Yes. Mixed-use residential property is acceptable provided the property has no greater than 25% (for a one story building); 33% (for a three story building); and 49% (for a two story building) of its floor area used for commercial (storefront) purposes. The rehab funds can only be used for the residential functions of the dwelling and areas used to access the residential part of the property.

Basically, yes, provided the lender can be assured that the contract sales price is reasonable or the existing debt on the property is low enough to assure a good equity position by the homeowner. On a HUD-owned property, the lender can use HUD's appraisal for the after-rehab value.

Yes. However, the property must be advertised that it is eligible for financing with a FHA 203(k) loan. If the HUD-owned property is purchased with other funds, a FHA 203(k) loan can be made after the property is in the buyers name. In this case, cash back will be allowed to the borrower for a period of six months from purchasing the HUD-owned property

No. However, it is strongly suggested that the lender protect their interests to assure no liens are placed on the property.

Yes. A borrower can finance into the mortgage 100 percent of the cost of eligible energy efficient improvements, subject to certain dollar limitations, without an appraisal of the energy improvements and without further credit qualification of the borrower.